BPC

“Bid Process Coordinator (BPC) of the TBCB project has to provide to the Bidders a Survey Report for the Project at least forty-five (45) days prior to the Bid Deadline. 
The Survey Report shall include the suggested route with approximate route length, type of terrain likely to be encountered and its likely implication in terms of Right of Way (ROW), statutory clearances, location of substations or converter stations and land area to be acquired for the substation or converter station. For Transmission Schemes to be implemented through TBCB, MoP may appoint CTUIL as one of the survey agency for survey works. After completion of survey works, CTUIL will submit the report to the respective BPC.”